Wednesday, January 11, 2012

Construction Update 1.11.2012


Construction Update – January 11, 2011
Applied Technology Center (ATC) – This new construction is approximately 64,000 SF and is being partially funded by the State of Illinois through the Capital Development Board.  The facility will house the comprehensive Automotive Programs, Ford Asset, Collision Repair, Industrial Technology, and Welding.  Interior masonry and metal walls are almost complete, and mechanical systems are continuing to be installed.  Exterior windows and overhead doors are being installed currently.  The project is scheduled to be ready for classes in fall 2012.
Automotive Lab

 
Automotive Lab North Side

Window Installation, South Side 

South Collision Overhead Doors

Paint Booth Area in Collision Lab

Wing Remodeling –The X Wing  2nd and 3rd floors have new carpet and stair treads installed. Trim work and remodeling are continuing.



3rd Floor X Wing Study Area

 
New Stair Flooring


Student Services Center – This project is approximately 96,000 SF of new space that will house all student service functions, including additional student lounge and food service space.   Architects Perkins and Will have completed the design and construction documents, and the Capital Development Board has approved all plans.  Bids will be opened on January 12, 2012, with results presented for Board of Trustee approval at the January 2012 Board meeting.  Construction should begin in spring 2012.  The intent is to have the facility completed in fall of 2013 or spring of 2014.





Fitness Center – This project is an addition to the existing Dodds Athletic Center.  The completion of this project would give the College a new "state of the art" athletic facility with space for Kinesiology, dance and aerobics, strength training, an indoor walking track, new locker rooms and team rooms, and coach’s offices.  Included in this project would be the remodeling of the lower level of the gymnasium.  Remodeling of the locker rooms and team rooms is complete, and restrooms should be completed by January 15. The new addition site work is on schedule with the walls, floors, and structural steel work completed.   Work on the new north entryway is underway, as is roofing and initial installation of mechanical systems.  Completion of the project is scheduled for August of 2012.

Exterior Looking Southwest

North Exterior and New Entry Area

Interior Fitness Area

Men’s Restroom Remodel


Roof Repair Phase IIThe second phase of roof repair and replacement was started in August.  Work on the Dodds Athletic Center, the L Wing, and the M Wing are underway.  New metal roof panels are being installed on sloped roof areas, and single ply rubber roofing is being installed on all flat roof areas. The contractor has completed work in the M Wing and athletic center and is working on roofs on the L Wing as weather allows.  The project is scheduled to be completed in May 2012.

 
L Wing Roof Ready for Metal Shingles

A Wing Roof Partially Complete
  